Standstill period (Stillhaltefrist)

The standstill period is a statutory waiting period between informing bidders of the award decision and actually awarding the contract.

Summarise with AI

What does standstill period mean?

The standstill period, also called the information and waiting period, is a statutory period above the EU thresholds during which the contracting authority may not award the contract after announcing the award decision. It protects bidders' rights by giving unsuccessful bidders time to examine the award decision and, if necessary, start a review procedure before the contract is validly concluded.

The standstill period is at least ten calendar days if the advance notice of the award decision is sent by fax or electronically, and at least 15 calendar days if it is sent by other means. The period starts on the day after the information is sent to the bidders. During this period, the contracting authority may not award the contract. A violation of the standstill period can make the concluded contract void.

The advance notice that triggers the standstill period must contain certain minimum content. The contracting authority must inform each unsuccessful bidder of the name of the company that is to receive the contract and of the reasons why its own bid was rejected. The contract may only be awarded after the standstill period has ended and only if no application for review has been received.

Relevance for bidders

The standstill period is of outstanding importance for bidders, because it defines the time window for starting a review procedure. If a bidder receives a rejection, it must decide within this period whether to accept or challenge the award decision. A quick analysis of the reasons for rejection and prompt legal advice are therefore essential.

After receiving the advance notice, bidders should check without delay whether the stated reasons for rejection are understandable and lawful. If there are doubts, the procurement violation must first be raised as a complaint (Rüge) with the contracting authority. If the complaint is unsuccessful, an application for review can be filed with the public procurement tribunal (Vergabekammer) within the standstill period. If the bidder misses the standstill period, it generally loses its right to a review.

Legal framework

The standstill period is governed by Section 134 GWB (German Act against Restraints of Competition). The duty to give advance notice also follows from Section 134 GWB. The legal consequence of violating the standstill period, namely that the contract is void, is set out in Section 135(1) No. 1 GWB. At EU level, the standstill period goes back to Remedies Directive 2007/66/EC. Below the thresholds, there is no statutory standstill obligation, although some procurement rules provide for information obligations.

Related terms

Single-stage procurement procedure
A single-stage procurement procedure is a procedure in which all bidders submit their bids in a single phase, without a preceding participation contest.
Subcontractor
A subcontractor is a company that the main contractor hires to carry out certain parts of a public contract.
Review procedure (Nachprüfungsverfahren)
The review procedure is the formal legal remedy that lets bidders challenge violations of procurement law above the EU thresholds before the public procurement tribunal (Vergabekammer).
Advance award notice (Vorabinformation)
The advance award notice is the statutory notice in which the contracting authority informs unsuccessful bidders of the intended award decision.
Award period (Zuschlagsfrist)
The award period is the time within which the contracting authority must award the contract to a bid before the bidders are no longer bound by their bids.
Participation deadline (Teilnahmefrist)
The participation deadline is the period within which companies must submit their request to participate in a two-stage procurement procedure.
Application deadline (Bewerbungsfrist)
The application deadline is the deadline within which companies must submit their request to participate in a procurement procedure with a preceding participation contest.
Document request period (Anforderungsfrist)
The document request period is the period within which companies can request the procurement documents from the contracting authority.
Delivery deadline
The delivery deadline is the period within which the contractor must perform the contractually owed work or deliver goods.
Bid deadline
The bid deadline is the deadline set by the contracting authority within which bidders must submit their bids.